Main Street Grade Separation 

Traffic Impacts

  • Notice of weekend road closures - Main Street East from Ontario Street  to east of the CPR tracks - to accommodate rail way track diversions and storm sewer installation:
    • Saturday, May 5, 12:00 a.m. to Monday, May 7, 5:00 a.m. and
    • Saturday, May 12, 12:00 a.m. to Monday, May 14, 5:00 a.m.
  • Notice of long-term lane restrictions: Main Street East from the Milton Mall Entrance to Wilson Drive: April 11, 2012 for approximately 24 months

Why a Grade Separation?

In 2007, Milton Council identified the need to eliminate the level crossing of the Canadian Pacific Railway (CPR) tracks at Main Street East, just east of Ontario Street.

Building an underpass will improve traffic flow on Main Street. It will also allow for better access to the downtown business area and central business district, as commercial development continues to increase on Main Street.

The environmental benefits will result from separating road vehicles from train traffic and eliminating idling while traffic waits for trains to clear the crossing. Public safety will also be improved, as this crossing currently has very high train/vehicle exposure.

Project Description

The project involves the construction of an underpass to the south side of the existing Main Street railway level crossing.

It is a structurally challenging project due to the sharp angle at which the CPR tracks cross Main Street. As a result, project features will include:

  • A long bridge span over the underpass
  • A new S-curve road alignment
  • Sidewalks level with the underpass roadway (not elevated)
  • The creation of a new service road for existing businesses to the north of the existing roadway
  • Roadway lighting, traffic signals, storm sewers, retaining wall construction and landscaping

Design

As the bridge will be a landmark to the Town, a great deal of consideration is being placed into its design. The concept is to create an urban focal point that echoes the natural landscape of the community.

Design concepts are available in several media:

Cost

The total project cost is estimated at $49 million, and the project is expected to take four years to complete. The project is partly funded by the Government of Canada through Canada's Gas Tax Fund.

Schedule

Stage(Estimated) Completion Date Status
Environmental Assessment 2007Complete
Design Summer 2011Complete
Construction Tender Summer 2011Complete
Construction Stage 1A: Milton Mall parking lot: temporary lot construction and rehabilitation of Main lot, removal of service tracks and grading for rail diversionSpring 2012Underway
Construction Stage 1B: Construct Milton Mall retaining wall, restoration of mall parking lot, and construction of 2 west spans of bridge structureSummer 2013Pending completion of Stage 1A
Construction Stage 2A: Construct southern half of 2 east spans, complete eastbound lanes of re-aligned Main Street Late 2013

Pending completion of Stage 1B

Construction Stage 2B: Construct northern half of 2 east spans, complete eastbound lanes of re-aligned Main StreetSummer 2015

Pending completion of Stage 2A

Construction Stage 3: Complete construction of service road Fall 2015Pending comlpetion of Stage 2B

"On Track" E-newsletter

Subscribe to On Track and receive regular updates on the Main Street Grade Separation project.

Issues

Additional Information

Maps, Drawings and Notices

Staff Reports

News Releases