2026 Projects

The Town of Milton is building a complete community and investing over $57 million in roads, bridges and stormwater infrastructure in 2026. While this investment reflects the 2026 approved budget, there are also projects being completed this year that were approved in previous budget years.

This investment in the community helps us put the right infrastructure in place to meet community needs and make Milton a Place of Possibility. 

What to expect this year 

This year, residents can expect road closures and lane restrictions on both main arterial roads and side streets. The Town of Milton extensively coordinates the timing of construction projects with Halton Region and the private sector as much as possible. Notices will be delivered to residents directly affected by construction prior to construction start.

2026 Infrastructure Construction Projects 

The projects listed blow are critical construction initiatives for 2026, aimed to maintain and develop an efficient civil infrastructure network in Milton.

Where 

What 

When 

Various locations 

Annual Asphalt Overlay Program on various streets throughout Milton. Work includes asphalt replacement and localized curb, gutter and sidewalk repairs, where required. Residents will receive notice before construction begins. 

Annual program. Anticipated to begin in May and continue through fall 2026. 

First Line Nassagaweya (11032 First Line Nassagaweya to 20 Side Road) and No. 2 Side Road (Bell School Line to Tremaine Road) 

Annual Expanded Asphalt Program, including asphalt rehabilitation and paved shoulder improvements where space permits. Culverts may be replaced where required. 

Annual program. Anticipated to begin in June and continue through Sept. 2026. 

Appleby Line (Derry Road to south of hairpin turn) 

 

Urbanization and drainage improvements localized retaining walls and traffic calming measures. 

Tree clearing completed in March. Construction anticipated to begin in May and continue through fall 2026. 

Fifth Line (Derry Road to Britannia Road) 

Utility relocations will be completed in advance of future road widening and urbanization work. 

Preliminary work in 2026. Major construction is planned to begin in 2027 and continue over multiple years. 

 

Thompson Road (west side between Clark Boulevard and Gas Easement) 

Localized multi-use path and boulevard improvements. 

Tender in spring with construction anticipated during July and August 2026. 

Mill Pond / Garden Lane 

Final restoration work, including paving and sidewalk improvements on Garden Lane where required. 

Anticipated in late spring or early summer and coordinated with Rotary Park and Community Centre operations. 

Esquesing Line and No. 5 Side Road Signalization 

 

Signalization improvements and associated intersection upgrades. Joint project with Halton Hills. 

Final works carried over from the 2025 contract. Completion anticipated in spring or summer 2026. 

Nipissing Road and Childs Drive Improvements 

Reconstruction of Nipissing Road and widening of Childs Drive from Ontario Street to Nipissing Road. Includes road widening, urbanization, a sidewalk, multi-use pathway and additional turning lanes. 

Construction is underway and anticipated to be completed in fall 2027. Learn more about the project.

Morobel Drive 

Urbanization and drainage improvements. 

Construction anticipated to begin June 1. 

Pearl Street (Commercial Street to dead end west of creek) 

Semi-urbanization and drainage improvements. 

Summer 2026 construction anticipated. 

Guiderail Program (various locations) 

Updates and replacement of post-and-cable guiderail systems. 

Summer 2026 construction anticipated, subject to tender timing. 

Retaining Wall Work (Millside Drive and Main Street) 

Reconstruction of the retaining wall. 

Summer tender anticipated, with construction planned for summer and fall 2026. 

Traffic Calming and Raised Crosswalk Installations 

Installation of speed cushions, signage, pavement markings and raised crosswalks near schools and on collector roads. 

Tender in spring with construction anticipated during July and August 2026. 

Stormwater Management Facility Rehabilitation (Ponds 2, 4 and 8) 

Final plantings and site cleanup. 

Anticipated spring or early summer 2026. 

Ontario Street Rehabilitation 

Completion of outstanding sidewalk, curb and asphalt work. 

Anticipated April to June 2026. 

 

Contact Engineering and Infrastructure