Extension of Main Street East
|
MCEA work started in 2023, with detailed design anticipated to start in late 2026, and construction anticipated to start in 2028 (Fifth to Sixth Line).
|
Fifth Line to Sixth Line
|
New road construction of Main Street East extension. Will require a Schedule C Municipal Class Environmental Assessment (MCEA) for the corridor from Fifth Line to Trafalgar Road. Learn more.
|
|
James Snow Parkway Multi-Use Path
|
Detailed design underway and construction anticipated to start in 2027.
|
Steeles Avenue to Esquesing Line – West side
|
Multi-use path reconstruction/replacement.
|
|
Reconstruction of Sixth Line
|
MCEA work started in 2024, with detailed design to follow in 2027/2028, and construction anticipated for 2030. Ultimate timing for construction dependent on development.
|
Highway 401 to Britannia Road
|
Reconstruction of Sixth Line to include potential widening and urbanizing which will require a Schedule C Municipal Class Environmental Assessment (MCEA).
|
|
Louis St. Laurent Avenue Extension
|
MCEA work anticipated to start in 2026, with detailed design anticipated to follow in 2028 and construction anticipated to start in 2030.
|
Louis St. Laurent Avenue – Fifth Line to SixthLine
|
New road construction of Louis St. Laurent Avenue extension. Will require a Schedule C Municipal Class Environmental Assessment (MCEA).
|
|
Peru Road – Cul de Sacs and Bridge Removal
|
Preliminary design and EA work commenced in 2022 with construction originally anticipated for 2024, however will ultimately be refined during the budget and capital forecasting process in the future in coordination with other projects in the area, and will depend on surrounding development timing, external agency approvals and land acquisition requirements.
|
Peru Road at Structure 8, approximately 850m north of Steeles Avenue
|
Removal of existing structure and installation of cul-de-sacs on both the north and south legs of Peru Road/on either side of the crossing location.
|
|
Expanded Asphalt Program-Various Locations – 5 segments of rural roads have been included in the 2027 program
|
Annual Program - anticipated to start in June and continue until September 2027.
|
Preliminary list of roads includes segments of:
Fourth Line Nassagaweya, No 15 Side Road, Ried Side Road, and Second Line Nassagaweya
|
Annual Expanded Asphalt program - Scope of work is focused on asphalt rehabilitation, and implementing a paved shoulder where space permits. Cross culverts may be replaced if identified during detailed design.
|