Construction notice

This project includes:

  • Localized storm sewer pipe and structure rehabilitation
  • Curb and sidewalk replacement
  • Concrete road base repairs
  • Full-depth base and surface course asphalt replacement

Location

Ontario Street, from Main Street East to Laurier Avenue

Schedule

Oct. 15, 2025, to Oct. 31, 2025

Lane Closures

There will be no full road closures during this stage. However, localized lane closures will be required, including night work at intersections. 

Stage 2A – Oct. 15 to late October 

  • Southbound lanes from Oak Street/Childs Drive to Donald Campbell Avenue will be closed
  • Southbound traffic will be diverted into the northbound lanes

Once Stage 2A is complete, all lanes will reopen before Stage 3 begins.

Note: All timelines are weather-dependent and may change. Stay updated at milton.ca/RoadClosures.

Investing in the Roads to Possibility

The Town of Milton is investing in community infrastructure to make your travel safe and accessible. We thank you for your patience. During construction, the public is encouraged to plan travel in advance, consider alternate routes, follow signage and be patient while traveling in and around construction areas.

Town-led construction is essential municipal work to ensure Milton’s infrastructure remains safe, in state of good repair and able to meet the community’s needs now and in the future. For more information road closures throughout the Town, visit our road construction page.