The Town of Milton is building a complete community and investing over $57 million in roads, bridges and stormwater infrastructure in 2026. While this investment reflects the 2026 approved budget, there are also projects being completed this year that were approved in previous budget years.

This investment in the community helps us put the right infrastructure in place to meet community needs and make Milton a Place of Possibility. 

What to expect this year

This year, residents can expect road closures and lane restrictions on both main arterial roads and side streets. The Town of Milton extensively coordinates the timing of construction projects with Halton Region and the private sector as much as possible. Notices will be delivered to residents directly affected by construction prior to construction start.

2026 infrastructure construction projects

The projects listed blow are critical construction initiatives for 2026, aimed to maintain and develop an efficient civil infrastructure network in Milton.

2026 construction projects

Where

What

When

Various Locations – 27 different roads for the 2026 Asphalt Overlay program. Locations are typically within the urban area and rural estate subdivisions.

Annual Asphalt Overlay program on various streets throughout Milton.  Includes removal and replacement of asphalt, as well as concrete work (curb, gutter, sidewalks), when required.  Notices will be delivered to affected residents prior to construction start. 

Annual Program - anticipated to start in May and continue with completion fall 2026. 

First Line Nassagaweya  (11032 First Line Nassagaweya to 20 Side Road) and No. 2 Side Road (Bell School Line to Tremaine) 

Annual Expanded Asphalt program - Scope of work is focused on asphalt rehabilitation, and implementing a paved shoulder where space permits. Cross culverts may be replaced if identified during detailed design. 

Annual Program - anticipated to start in June and continue until September 2026.

Appleby Line – Derry Road to south of hairpin turn 

Urbanization and drainage improvements, localized retaining walls and traffic calming measures. 

Tree clearing complete in March, construction anticipated to start in May and continue to fall 2026.

Fifth Line – Derry to Britannia 

 

Utility relocations this year; major reconstruction (widening, urbanization) to follow.

Preliminary works this year (2026) with major construction to follow in 2027 over multiple years.

Thompson Road – west side between Clark and Gas Easement 

Localized multi-use path and boulevard works.

Tender in spring with construction during July and August 2026.

Mill Pond/Garden Lane 

Final restoration works including paving and sidewalk works on Garden Lane as required.

Anticipate late spring/early summer – requires coordination with facilities/recreation regarding Rotary Park and Community Center use

Esquesing Line & No. 5 Side Road Signalization 

Signalization of intersection including associated improvements. Joint project with Halton Hills.

Finishing works, carry over from 2025 contract, to be completed spring/summer 2026.

Nipissing Road and Childs Drive Improvements 

Reconstruction of Nipissing Road and widening of Childs Drive from Ontario Street to Nipissing Road. The design includes urbanization and widening of Nipissing Road from 2 lanes to 3 lanes and the construction of a sidewalk and a multi-use pathway along the roadway. Childs Drive will be widened to the south to accommodate the addition of designated turning lanes.  Right turn lane will be constructed on north bound Ontario Street to eastbound Childs Drive.

Construction is underway and is planned to be completed in fall 2027.

Morobel Drive – entire length 

Urbanization (no sidewalks), drainage improvements.

Targeting construction start on June 1.

Pearl Street – Commercial to dead end (west side of creek) 

Semi-urbanization, drainage improvements 

Summer construction start anticipated.

Guiderail Program – various locations

Smaller program, targeting updates/replacements of post and cable guiderail.

Anticipated summer construction/pending tender timing.

Retaining Wall Work – Millside Drive and Main Street 

Rebuilding the retaining wall.

Anticipate summer tender for summer/fall 2026 construction.

Traffic Calming and Raised Crosswalk Installations

Various locations – installation of speed cushions, signage and line painting, and raised cross walks along school frontages on collector roads. 

Tender in spring with construction during July and August 2026.

Stormwater Management Facility Rehabilitation – Ponds #2, #4 & #8  Final plantings and site clean up. Anticipated Spring/Early Summer 2026.
Ontario Street Rehabilitation   Complete outstanding concrete work (sidewalk both sides, curb on the east side), base asphalt (east side) and surface course asphalt. Anticipated April to June 2026.