The Town of Milton is building a complete community and investing over $49.78 million in roads, bridges and stormwater infrastructure in 2025. While this investment reflects the 2025 approved budget, there are also projects being completed this year that were approved in previous budget years.
This investment in the community helps us put the right infrastructure in place to meet community needs and make Milton a Place of Possibility.
What to expect this year
This year, residents can expect road closures and lane restrictions on both main arterial roads and side streets. The Town of Milton extensively coordinates the timing of construction projects with Halton Region and the private sector as much as possible. Notices will be delivered to residents directly affected by construction prior to construction start.
Major 2025 projects
The projects listed below are major construction initiatives for 2025, aimed to maintain and develop an efficient civil infrastructure network in Milton.
2025 construction projects |
||
Where |
What |
When |
Various locations – approximately 11km of roads for the 2025 Asphalt Overlay Program. Locations are typically within the urban area and rural estate subdivisions. |
Annual Asphalt Overlay program on various streets throughout Milton. Includes removal and replacement of asphalt, as well as concrete work (curb, gutter, sidewalks), when required. Notices will be delivered to affected residents prior to construction start. |
Annual program anticiapted to start in May and continue through the summer with completion in the fall of 2025. |
Kelso Road from Park Entrance to RR22-Tremaine Road
No 15 Side Road from RR1-Guelph Line to Fourth Line Nassagaweya
Sixth Line from 1.8Km North of Lower Base to RR6-Britannia Road |
Expanded Asphalt Annual program, with 2025 program, Scope of work is focused on asphalt rehabilitation, and implementing a paved shoulder where space permits. Cross culverts may be replaced if identified during detailed design. |
Annual Program - anticipated to start in June and continue until September 2025. |
Milburough Line from Regional Road 7 (Derry Road) to Concession Road 10 East (Hamilton) |
Scope of work is focused on asphalt rehabilitation, and implementing a paved shoulder where space permits. Cross culverts may be replaced if identified during detailed design. Joint contract with the City of Hamilton. |
Construction is anticipated to start in June and be completed by September 2025. |
Ontario St. (Main Street East to Derry Road) |
Scope of work for this project includes storm sewer and asphalt paving rehabilitation. |
Construction is anticipated to start in June and be completed by November 2025. |
Nipissing Road and Childs Drive Improvements |
Reconstruction of Nipissing Road and widening of Childs Drive from Ontario Street to Nipissing Road. The design includes an urbanization and widening of Nipissing Road from 2 lanes to 3 lanes and the construction of a sidewalk and a multi-use pathway along the roadway. Childs Drive will be widened to the south to accommodate the addition of designated turning lanes. Right turn lane will be constructed on north bound Ontario Street to eastbound Childs Drive. Joint project with Halton Region. |
Construction is anticipated to start in summer 2025 and be completed in summer 2027. |
5 Side Road & Esquesing Line |
Signalization of intersection including associated improvements. Joint project with Halton Hills. |
Construction is anticipated to start in June and be completed by September 2025. |
Louis St. Laurent Avenue from Tremaine Road to Regional Road 25 |
Boulevard and median works, including localized landscaping improvements. |
Construction is anticipated to be completed Spring 2025. |
Storm Sewer Rehabilitation Program – Various locations within the Town’s urban area |
Annual Storm Sewer Rehabilitation program on various streets throughout Milton. Includes CCTV investigation, and storm sewer rehabilitation which may include the removal and replacement various storm sewer components such as maintenance holes, catch basins and storm sewer pipe. |
Construction to commence in summer of 2025, with completion anticipated in late fall 2025. |
Jasper Street |
Rehabilitation of entire roadway, focusing in pavement improvements. |
Design is substantially completed, with construction is anticipated to start in summer 2025. |
Fourth Line Nassagaweya Bridge – Structure 112 - At structure location on Fourth Line Nassagaweya (approximately 2.2km north of 25 Side Road) |
The proposed works include structure replacement with associated grading and restorations. |
Construction to commence in summer of 2025, with completion anticipated in late fall 2025. |
Pond Sediment Removal projects have been identified for construction in 2025 (Pond #4 – 1015 Trudeau Dr.), 2026 (Pond #2 – 1051 Fourth Line and 2027 (Pond #8 – 140 Livingston Rd.) |
Removal of accumulated sediment from forebay/main cell of various SWM facilities. Other documented deficiencies such as concrete repairs, grading, clean-up of vegetation will be completed at the same time. |
For type of project, ponds will be identified as candidates for sediment removal through work completed with SWM Facility Asset Management Plans scheduled every 5 years beginning in 2025. |
2025 Bridge and Culvert Rehabilitation Program |
Design started in 2023, with construction work begining in 2025. |
Biennial program for bridge and culvert rehabilitation works – including concrete patching, guiderail and end-treatment replacements. |
Contact Us